Renovating a House in the Dominican Republic: Permits, Contractors and Costs

Renovating a House in the Dominican Republic: Permits, Contractors and Costs

Short answer: Work that adds floor area or changes the structure, the exterior, the volume or the use of a house needs a license or a license modification from the housing ministry MIVHED, built on municipal certificates; building without authorization is a serious infraction under Law 368-22. For purely cosmetic work we found no citable rule, so ask the municipality in writing. If the older house has no license, the renovation becomes a regularization with a structural evaluation. Contract in writing, pay by inspected stage and keep an independent supervisor.

This is general information; a Dominican attorney and a licensed engineer or architect review your project. The guide covers a house you own or are about to buy. For a new build see building a villa.

Which renovation work needs a permit?

The construction code treats as a building work any extension, modification, reform or rehabilitation that alters the architectural configuration or the use, meaning total interventions or partial ones that essentially change the exterior composition, the volume or the structural system (3.1.3.3 b). Plans for alterations must carry the building's earlier license (3.6.4.3) [1]. Beyond that line the sources are silent.

Work What the sources show
Paint, tiles, kitchen, bathroom fittings Not addressed in the sources we could cite; ask the municipal planning office in writing and keep the answer
Changes to layout, exterior, volume, structure or use A building work under the code [1]; license or modification of the existing license [2]
Added floor area or a new storey License modification, application fee RD$8,500; municipal 2.5% and CODIA 2% on the added value [2]
House that already has a license Original license, title, survey and, if land use, height or boundaries change, a municipal no-objection certificate [2]
Work already started with no inspection records Structural (vulnerability) evaluation by a consultant MIVHED qualifies [2]
House near the shoreline MIVHED lists a separate Ministry of Public Works (MOPC) authorization for the maritime strip [3]
Condominium unit No changes that affect safety or appearance (Art. 7); new floors or works affecting the building need all owners (Art. 8) [4]

Underneath all of it, Law 368-22 says no act of building is legitimate without prior administrative authorization (Art. 39), makes building without it a serious infraction (Art. 80) and sets fines of 101 to 1,000 public-sector minimum wages for serious infractions (Art. 82) [5].

What if the older house has no license or approved plans?

Then you are regularizing. The code says illegal works, built or under way without plans, permits and licenses, are sanctioned under Law 687, and the responsible party must apply to MIVHED for regularization: all documents for the license, and, where the work is finished or the main structure is built, structural plans backed by an evaluation report from an experienced structural-vulnerability consultant acceptable to MIVHED, with tests at the owner's cost. MIVHED may inspect, and the license issues after taxes and fines are paid (3.5.1.4 and 3.5.2) [1].

Ask for the license and approved plans before you sign, not after. Our guide to title due diligence lists the seller documents, and the viewing and buying guide shows where this fits in the process.

What do permits and inspections cost, and how long do they take?

The fees below are the stated MIVHED amounts, in Dominican pesos (RD$), read on November 14, 2026 [2][3].

Item Amount
Application, license modification RD$8,500
Municipal arbitrios 2.5% (of the added value for a modification)
CODIA arbitrios 2% (same base)
Staged inspection, residence up to 2 levels RD$3,300 per level for vertical elements and RD$3,300 per level for horizontal elements (up to 3 visits)
Final inspection, residence up to 2 levels RD$11,000

Example with assumed numbers: an extension adding RD$3,000,000 of construction value costs RD$8,500 plus RD$75,000 (2.5%) plus RD$60,000 (2%), so RD$143,500, before professionals' fees. At an illustrative rate of RD$60 per US dollar (a round figure used throughout our guides; the exchange rate fluctuates, so check the current rate), that is about US$2,392. For a one-storey house, MIVHED's staged and final inspection tariff adds RD$17,600, about US$293. MIVHED's page wording on the base for the 2.5% and 2% is not fully consistent, so ask which base applies.

Stated response times are up to 60 working days for non-complex projects and up to 120 for complex ones, and coastal zones count as complex. A license or modification is valid one year [2][3]. Free authorizations for preliminary works (5 or 10 working days) and for a partial start (5 working days) exist but require an application in process [3]. The final inspection is stated at 10 working days once the request is complete [6].

For the renovation itself we found no official cost per square metre for the north coast. The national statistics office's index of direct housing construction costs covers the Santo Domingo area only and excludes land, permits, financing and builder profit. Press reports of it show a 1.94% rise over twelve months to June 2026 and 6.42% to September 2026 [7][8]. Use it for drift, not as a price, and get at least two written quotes on the same scope.

How do you contract and pay a builder?

Put the price, scope and changes in writing. The Civil Code says that where a contractor builds to a plan agreed with the owner, he may not ask for more because labor or materials rose, nor for changes to the plan, unless the changes are authorized in writing and the price agreed (Art. 1793). The owner may end a contract made by the job (a destajo) on his own will, indemnifying the contractor (Art. 1794) [9].

Staged payments are your best protection, but we found no Dominican source that sets standard percentages, so we quote none. Note Art. 1791: for work of many parts, verification can be done by parts and is presumed done for every part paid in proportion to the work completed [9]. Inspect before you pay a stage.

A contract should state:

  1. Scope, plans and a materials schedule attached.
  2. Who obtains permits, and that no work starts before they exist. A Gestor Urbano, a professional MIVHED authorizes, can file for you; fees are agreed directly [3].
  3. Payments tied to inspected stages, not dates.
  4. A retained amount until the final inspection certificate and the defects list are closed.
  5. Changes only in writing, with price (Art. 1793).
  6. The warranty period. The code states ten years for structural damage, three for non-structural parts and installations, one for finishes (3.9.1) [1]; the Civil Code has ten years in Art. 1792 and five in Art. 2270, as modified in 1941 [9]. Ask your attorney which period the contract states.
  7. The final documents the code lists: provisional acceptance, social security and Labor Ministry certificates, a hidden-defects policy for the retained amount and tax and CODIA certificates (3.23.6) [1].

What are your obligations to the builder's workers?

The Labor Code says those who contract works for themselves and without subjection to the owner are employers, not intermediaries; but persons without own means to meet their obligations to workers are intermediaries and jointly liable with the principal contractor (Art. 12). Workers of a contractor may ask the owner to retain the wages earned that the contractor has not paid, and the owner pays them only under a court judgment or with the contractor's consent (Art. 14). Sums owed to contractors cannot be assigned or seized to the workers' detriment, and for such assignments or seizures to reach the final balance the contractor must first show the owner a Labor Department certificate of no wage claims (Art. 210) [10]. The Civil Code limits workers' direct claims against the owner to what the owner still owes the contractor (Art. 1798) [9].

In practice: keep a ledger of what you owe, pay stages against inspection, and hold the final installment until the Labor Ministry certificate arrives; the code lists that certificate among the final documents (3.23.6) [1]. Your attorney confirms how this applies to your contract.

Can you supervise a renovation from abroad?

Yes, with someone independent of the contractor. MIVHED runs staged inspections of authorized private works: an initial inspection of foundations, a structural inspection of walls, columns, floors, roofs and beams with installations checked as work advances, and a final inspection that only MIVHED performs. An owner can instead hire an accredited private technical supervisor for the first two [3]. Stated MIVHED response times are 5 working days for the initial inspection, 2 for the structural one and 10 for the final [3]. Release each payment against dated photos, the supervisor's sign-off and material invoices.

What do older coastal houses hide?

Corroding reinforcement is the one you cannot see. A 2009 U.S. Federal Highway Administration report says the chloride level that starts corrosion varies by more than an order of magnitude, gives 0.6 kg per cubic metre of concrete as a low-end example and lists seawater and spray as a chloride source for coastal bridges [11]. The study concerns bridges, but the chemistry is the same. The Dominican code asks for special cover in corrosive environments under ACI 318-19 (5.4.3.6) [1]. Open suspect spots (cracked beam edges, spalled balcony slabs, column bases) before you price finishes; patching plaster over rusting bar hides it. Our guide to maintaining beachfront property covers routine care afterwards. For electrical and plumbing in older houses we found no citable source on typical defects, so put both in the inspector's written scope.

What should you ask before you start?

  1. Municipality: does this work need an authorization, and which office issues it? (We found no published checklist for Sosúa.)
  2. MIVHED: does the house have a license, under which regime, and what changes need a modification?
  3. Contractor: who is the responsible professional and what is the CODIA number?
  4. Contractor: how are payments, changes and the retained amount set?
  5. Insurer: does your cover continue while the house is open or under repair?
  6. Supervisor: who inspects, how often and do you receive the reports?

As of November 13, 2026, Instyle's inventory feed lists 60 houses and villas for sale (48 houses, 12 villas) among 170 properties; it does not record construction year or license status [12]. Browse houses for sale in Sosúa, or contact Instyle and ask for the paperwork a specific house has.

Frequently asked questions

Do I need a permit to renovate a house in the Dominican Republic? For work that adds area or changes structure, exterior, volume or use, yes: a MIVHED license or modification [1][2]. For cosmetic work the sources are silent, so ask the municipality in writing.

How long does a license or modification take? Up to 60 working days for non-complex projects and up to 120 for complex ones, which include coastal zones. A license is valid one year [3].

Can a foreigner apply for a construction license? MIVHED's page states no nationality condition and lists requirements around title, survey, certificates and plans [3]. Your attorney or a Gestor Urbano can file.

Can I renovate my condo without asking the other owners? Inside your unit generally, but not changes that affect safety or appearance, and new works affecting the building need all owners [4].

What does a permit cost? RD$8,500 to apply for a modification, plus 2.5% to the municipality and 2% to CODIA when area is added [2], before professionals' fees.

Sources

All retrieved November 14, 2026.

  1. MIVHED, Código de Construcción de la República Dominicana, Volume I, Tomo 1 (July 2026 edition): https://mivhed.gob.do/wp-content/uploads/2026/08/TOMO-1-VOLUMEN-1-JULIO-2026.pdf
  2. MIVHED, Modificación de Licencia de Construcción: https://mivhed.gob.do/permisos-y-licencias-de-construccion/modificacion-de-licencia-de-construccion/
  3. MIVHED, Licencia de Construcción y Permisos Asociados, and Inspección por Etapa de Obras Privadas: https://mivhed.gob.do/permisos-y-licencias-de-construccion/licencia-de-construccion-y-permisos-asociados/ and https://mivhed.gob.do/inspecciones-de-obras/inspeccion-por-etapa-de-obras-privadas/
  4. Ley 5038 de 1958 sobre Condominios, text published by Guzmán Ariza: https://drlawyer.com/espanol/leyes/ley-5038-de-1958-sobre-condominios/
  5. Ley 368-22 de Ordenamiento Territorial, Uso de Suelo y Asentamientos Humanos, text published by Guzmán Ariza: https://drlawyer.com/espanol/leyes/ley-368-22-de-ordenamiento-territorial-uso-de-suelo-y-asentamientos-humanos/
  6. MIVHED, Inspección por Etapa de Obras Privadas (final inspection, 10 working days): https://mivhed.gob.do/inspecciones-de-obras/inspeccion-por-etapa-de-obras-privadas/
  7. Diario Libre, "Subcontratos lideraron el alza del costo de construcción en junio 2026" (July 25, 2026, reporting ONE's ICDV): https://diariolibre.com/economia/vivienda/2026/07/25/subcontratos-lideraron-el-alza-del-costo-de-construccion-en-junio-2026/3609489
  8. Inmobiliario.do, "Costos de construcción de viviendas aumentan un 6.42 % en un año" (October 26, 2026, reporting ONE's ICDV for September 2026): https://inmobiliario.do/costos-de-construccion-de-viviendas-aumentan-un-6-42-en-un-ano/
  9. Código Civil de la República Dominicana, Arts. 1791 to 1794, 1798 and 2270 (text hosted by the OAS): https://oas.org/ext/Portals/33/Files/Member-States/sp_dom-int-text-cc.pdf
  10. Código de Trabajo (Ley 16-92), Arts. 12, 14 and 210, Ministerio de Trabajo (PDF): https://transparencia.mt.gob.do/images/docs/publicaciones/codigo-de-trabajo.pdf
  11. U.S. Federal Highway Administration, Corrosion Resistant Alloys for Reinforced Concrete, FHWA-HRT-09-020, Chapter 1 (2009): https://www.fhwa.dot.gov/publications/research/infrastructure/structures/09020/chapt1.cfm
  12. Instyle Investments, public inventory feed of the website, read November 13, 2026 (counts only; same counts on November 14): https://backend.instyleinvestments.com/api/oeffentlich/website
Justian HankeWritten byJustian HankeDigital Sales Executive

Keep reading

Homes for sale in Sosúa

See all 143

Popular searches

Villas for sale in Sosúa · Apartments and condos for sale in Sosúa · Houses for sale in Sosúa · Condos for sale in Cabarete · Condos for sale in Puerto Plata · Villas for sale in the Dominican Republic

Looking for property in Sosúa?

Tell us your budget and what you need — an agent who knows Sosúa will get back to you.